A/S Tukuma piens construction of a new production building

A/S Tukuma piens construction of a new production building

JSC “Tukuma Piens” is one of the largest milk processors in Latvia, cooperating with 225 suppliers, mainly in Kurzeme and Zemgale, and produces more than 180 different dairy products, including “Baltais Exports” brand fresh dairy products, “Baltais EKO” brand organic products: yogurts, cottage cheese, cream, kefir, etc

With the growing consumer demand for the products produced by JSC “Tukuma Piens”, the company needed to expand and reconstruct production facilities, as a result of which the company’s board decided to implement the project “Construction of a new production building for production needs”.

Within the framework of the project, a new production building was built, the necessary utilities were built and the territory was improved. As well as the installation of production equipment in the newly built production building and the start of the production process.

As a result of the project implementation, a production building was built and put into operation, which is intended for the expansion of the production plant of A / S “Tukuma Piens”, the production of cottage cheese and butter was started, including the maturation of other dairy products in the new production building. This allowed the company to develop these product segments by offering consumers ever new and unprecedented products.

 

Company JSC “Tukuma Piens”
Area of business One of the largest milk processing companies in Latvia, producing more than 180 different dairy products.
Name of the project Construction of a new production building for production needs
Project Nr. 3.1.1.5./16/A/024
Realization date December 2016 – September 2018
Support program Support for the investments in the development of processing and manufacturing infrastructure
Cooperation institution Central Finance and Contracting Agency
Aim of the project The general objective of the project is the construction of a new production building for production purposes, as a result of which the turnover and profit from economic activity in the dairy processing sector will increase.
Description of the project Within the framework of the project, the construction of the new production building, the construction of the necessary engineering communications, and the improvement of the territory took place; Also, only the installation of production equipment in the newly built production building and the start of the production process was performed.
Total costs 2 312 540.10 EUR
Planned co-financing of EU funds 959 643.45 EUR

 

 

More information: www.baltais.lv 

Leave a reply

Your email address will not be published. Required fields are marked *